VMware to Hyper-V Migration Case Study: What It’s Really Like

A VMware to Hyper-V migration case study drawn from real Australian projects: reusing SANs, Storage Spaces Direct, pilots, backups, downtime and what didn't go to plan.

At a glance

Core takeaway
The conversion is the easy part.
What to know
Every workload needs its own plan.
Common risks
Running out of migration storage.
Reality check
Sometimes VMware is still the answer.
How we help
We plan, pilot, migrate and protect.
Busy Australian retail distribution warehouse whose servers moved in a VMware to Hyper-V migration
"A successful migration isn’t one where nothing unexpected happens. It’s one where you’ve already thought about what you’ll do when it does. . . "

QUICK ANSWER

The Practical Starting Point: VMware to Hyper-V Migration Case Study

Moving off VMware is easy to talk about. This VMware to Hyper-V migration case study shows what it actually looks like.

Over the past couple of years, Intellect IT has planned and delivered VMware to Hyper-V migrations for Australian organisations in logistics, retail and other sectors.

Rather than focus on one customer, we’ve brought together real examples from several of those projects.

The biggest lesson is simple. Converting the virtual machines is only a small part of the job. The work around it is where experience counts.

Client names have been withheld for confidentiality. The examples are drawn from real Intellect IT projects.

WHAT TO KNOW FIRST

Key takeaways

Reuse what still makes sense

A new hypervisor doesn't automatically mean new servers or a new SAN. Check what can stay first.

Plan migration storage, not just the end state

You need temporary space to move workloads across. It's one of the easiest things to overlook.

Ten VMs aren't ten identical jobs

One large application server can need more planning than several small VMs combined.

Pilot before the critical systems

Measure real migration speed on lower risk servers before you lock in outage windows.

Backups move last

Keep the old VMware protection until the new Hyper-V backups are proven to work.

Start six months out

Time gives you options. A looming renewal takes them away.

How these migrations ran

A real VMware to Hyper-V migration, step by step

Every project followed the same shape. Understand the environment, prove the approach on low risk servers, then move the critical systems with a way back.

DiscoverEvery VM, its size, operating system and dependencies.
PilotReal transfer speeds measured before the critical outage windows.
RetireVMware is only switched off once backups and systems are proven.

Where these VMware to Hyper-V migrations started

The reasons for looking at a move varied.

For a large Australian retailer, VMware end of support was the trigger to review the platform rather than simply carry on. The business moved to Windows Server 2025 Hyper-V and kept its existing shared SAN.

For a national Australian business, the VMware renewal date became the project deadline. The opportunity was to reuse the existing servers and SAN, but only after confirming the hardware, storage and Windows Server licensing supported the new design.

That’s why we recommend starting around six months before your renewal. The question isn’t just “Can we replace VMware with Hyper-V?” It’s “If we were designing this environment today, what would we build?”

Why it matters

“A successful migration isn’t one where nothing unexpected happens. It’s one where you’ve already thought about what you’ll do when it does.”

Max Soukhomlinov Intellect IT Director

New to the series? Start with whether to move from VMware to Hyper-V, our Hyper-V vs VMware comparison, and Windows Server Standard vs Datacenter.

VMware to Hyper-V migration case study: three projects side by side

Here’s how three of these migrations compared.

Three VMware to Hyper-V migrations compared
Case 1: National business Case 2: Large retailer Case 3: National logistics
OrganisationA national Australian businessA large Australian retailerA national logistics organisation
TriggerVMware renewal date became the project deadlineVMware end of supportPlatform review and modernisation
New platformHyper-V on the existing serversWindows Server 2025 Hyper-V, two-node failover clusterWindows Server 2025 Hyper-V, two-node failover cluster
StorageExisting iSCSI SAN reusedExisting SAN kept as Cluster Shared VolumesStorage Spaces Direct, plus existing SAN where it made sense
Migration styleProgressive, group by groupConverted and migrated, then VMware retiredWorkload by workload, each with its own method
Main challengeNot enough free SAN space for a second copy of about 8.6 TBMoving backups and monitoring at the right timeVery different workloads, from RDS to a large file server
Key lessonPlan temporary migration storageKeep what still worksPlan workload by workload, not VM by VM

Case 1: Reuse what makes sense

A national Australian business had a VMware environment running on hardware that still had useful life. Replacing everything just because the hypervisor was changing didn’t make commercial sense.

The plan was to reuse the existing servers and iSCSI SAN, build the Hyper-V environment and migrate workloads progressively.

It wasn’t quite that simple. The SAN didn’t have enough free space to hold a full second copy of about 8.6 TB of workloads.

So instead of buying a bigger SAN, we changed the approach. Each group of VMs was migrated, checked on Hyper-V, and only then was the old VMware copy retired and its storage reclaimed for the next group.

Planning also found a single VM bigger than the 5 TB of migration space available. Finding that early meant there was time to clean up data and choose another approach, rather than discovering it on the night.

  • The business benefit: The client could keep infrastructure it had already paid for, instead of funding a full hardware replacement.
  • The lesson: Check storage for the migration itself, not just the finished environment. Temporary space is easy to overlook.

Case 2: Sometimes keeping the SAN is the right answer

For a large Australian retailer, there was no reason to replace perfectly good shared storage just because VMware was going.

We deployed Windows Server 2025 Hyper-V across two nodes, set up Windows Failover Clustering and connected the existing SAN as Cluster Shared Volume storage.

Workloads were converted and migrated. Only then were the VMware backups and monitoring retired.

  • The business benefit: High availability stayed in place, and the platform changed without replacing everything underneath it.
  • The lesson: A VMware to Hyper-V migration doesn’t have to become a full data centre replacement. Keep what still makes sense. Replace what doesn’t.

Case 3: Sometimes it’s a different architecture

A national logistics organisation needed something different again. Workloads moved to a two-node Windows Server 2025 Hyper-V failover cluster, using Storage Spaces Direct alongside existing SAN storage where it made sense. Backup and monitoring moved across as part of the project.

This project showed why a migration is planned workload by workload, not just VM by VM.

  • Some servers: Migrated directly.
  • Older systems: Replaced side by side on newer operating systems.
  • Remote Desktop servers: Moved in batches after a pilot and user testing.
  • A large file server: Needed its own outage window of several hours, because of its size and testing.
  • Database and application servers: Each needed its own approach.

The project also uncovered a chance to improve security. Rather than leave workstations, Remote Desktop and backend servers together, the new design separated user facing systems from backend infrastructure, with firewall controls between them. Doing it during the migration was far less work than coming back later and moving everything again.

  • The business benefit: Each system moved in the way that best balanced risk, downtime and business impact.
  • The lesson: Ten VMs don’t mean ten similar migrations. And a migration is the best time to fix what you’d otherwise live with for years.

Pilot first, and protect your backups

One rule runs through every VMware to Hyper-V migration we do: don’t make your most important server the first one you move.

On one project, lower risk VMs were used to measure real migration speed before the final after-hours windows were locked in. Until you test it, you don’t know how fast your particular mix of storage, network and tools will move the data.

A national professional membership organisation took the same careful approach. VMware and Hyper-V ran side by side, systems moved in stages, and the original VMware VMs stayed as a way back until the new ones were tested.

Backups need their own plan

A server starting up on Hyper-V isn’t enough. It has to be protected.

  • Reconfigure: Point backup services at the new Hyper-V workloads.
  • Validate: Confirm backup jobs and replication are actually succeeding.
  • Update monitoring: Make sure alerts cover the new platform.
  • Only then retire: Remove the VMware protection last, never first.

It isn’t exciting. But it’s exactly the detail you want someone thinking about when they’re moving your production systems.

What didn’t go to plan in our VMware to Hyper-V migrations

Real environments aren’t clean. They’ve grown over years. Across different projects, we’ve run into:

  • Very large VMs: Some didn’t fit in the migration storage first available.
  • Older operating systems: These needed a different migration approach.
  • BIOS and partition compatibility: Some VMs needed extra checks before they could move.
  • Application reactivation: Some software needed reactivating once the virtual hardware changed.
  • Printer configurations: These had to be documented before any server changes.
  • Storage limits: These changed the order workloads were moved in.
  • Network segmentation: Cheaper to fix while servers were already moving.
  • Backup and DR timing: These had to move at exactly the right point.

None of these made a migration unworkable. They just needed finding before they became surprises.

And sometimes the answer is to stay on VMware

Hyper-V isn’t automatically the right answer, and our projects prove it.

For a transport organisation, we’ve delivered and supported a stretched VMware vSAN design across two data centres, with large storage, automatic failover, substantial backup infrastructure and complex disaster recovery needs.

That’s a very different environment from a typical two-host setup, and VMware was the right fit.

Because we work with both platforms, we don’t start with “How do we get you onto Hyper-V?” We start with “Which platform actually makes sense for you?”

How long does a VMware to Hyper-V migration take?

There’s no honest answer based only on the number of VMs.

A simple environment with supported operating systems and compatible hardware can move fairly quickly. Others involve new hardware, large data volumes, application owners, operating system upgrades, vendors and tight outage windows.

  • Smaller workloads: Planned outages of around one to two hours.
  • Larger systems: Four to seven hours, including migration and testing.
  • The whole project: Depends on how much discovery, building and testing your environment needs.

In one recent production migration, several critical workloads moved from VMware to Hyper-V within the approved maintenance window, faster than planned. The team took backups first, checked storage, moved workloads in stages, validated each one and monitored all weekend. Afterwards the environment was stable, the cluster was healthy and backups were completing.

Having a Plan B mattered too. It gave the client flexibility around the final cutover and the timing of their licensing.

Start around six months before renewal

That doesn’t mean a VMware to Hyper-V migration takes six months. It means there’s time to find the things nobody knew about, before the deadline forces your hand.

Which VMware to Hyper-V migration tool should you use?

We’re often asked which tool to use. The tool matters less than the planning around it, but it does change how much downtime you need.

Here are the main options for a VMware to Hyper-V migration and where each one fits.

ToolBest forCostDowntime
Windows Admin Center VM ConversionSmall to medium environments managed through vCenter, up to 10 VMs per batchFreeMinimal. VMs copy across while running, then shut down briefly for a final sync. Still in preview.
StarWind V2V ConverterStandalone ESXi hosts and one-off VMsFreeUsually a shutdown per VM, though a sync option can reduce it.
Veeam Backup & ReplicationLarger production workloads, especially if you already use VeeamPaidVery low. Instant Recovery can run a VMware backup straight onto a Hyper-V host.
System Center VMMBusinesses already running System CenterPaidA full outage per VM. VMs must be powered off, and VMs on vSAN storage aren’t supported.

Avoid Microsoft Virtual Machine Converter (MVMC) and Disk2VHD for production systems. MVMC has been retired and struggles with modern operating systems.

If you already run System Center, Microsoft’s guide to converting VMware VMs in VMM covers its limits, including powered-off conversions and no vSAN support.

A word on Windows Admin Center

Microsoft’s free Windows Admin Center VM Conversion extension is the one most people hear about first. It copies VMs while they keep running and only powers them off for a final sync at cutover.

It’s still in preview, so Microsoft doesn’t formally support it yet. It also works through vCenter and needs VMware PowerCLI and a specific VDDK version installed. Microsoft’s step-by-step migration guide lists the full requirements.

For a small environment that may be fine. For critical systems, it’s worth weighing up whether you want a supported tool behind you.

Technical checks before any VMware to Hyper-V migration

  • Build the Hyper-V side first: Hosts, storage (Cluster Shared Volumes or SMB) and virtual switches that match your existing VLANs.
  • BIOS or UEFI: BIOS VMs become Generation 1 Hyper-V VMs and UEFI VMs become Generation 2. Check each one.
  • Static IPs: Record them before you start, as network adapters change during conversion.
  • Passthrough hardware: Remove vGPU or SR-IOV devices, which won’t come across.
  • Linux servers: Install Hyper-V drivers before migrating, or the VM may not boot.
  • Clean up afterwards: Remove VMware Tools and check Hyper-V Integration Services are running.

These details sit behind the “what didn’t go to plan” list above. Getting them right during planning is what keeps cutover windows short.

OUR DELIVERY MODEL

How Intellect IT runs a VMware to Hyper-V migration

1

Phase 1 – Discovery and assessment

  • Every workload: We record each VM, its size, operating system and dependencies.
  • Hardware and storage: We check what can be reused, including migration headroom.
  • The business: We agree outage windows and who owns each application.
2

Phase 2 – Architecture and licensing

  • The right design: Reuse, keep the SAN, Storage Spaces Direct, or a mix.
  • 3, 5 and 10 year TCO: We model Standard, Datacenter or a mix over the life of the hardware.
  • Improvements: We look for things to retire, upgrade or separate while we’re there.
3

Phase 3 – Build and pilot

  • Build: We set up the Hyper-V hosts, cluster, storage and networking.
  • Pilot: We move lower risk VMs first and measure real transfer speeds.
  • Adjust: We refine the schedule before any critical system moves.
4

Phase 4 – Migrate in controlled groups

  • Staged moves: Production workloads move in groups, each with its own method.
  • Validation: Each system is checked with the people who use it.
  • A way back: The original VMware VMs stay until the new ones are proven.
5

Phase 5 – Protect, retire and hand over

  • Backups and DR: New protection is validated before the old is removed.
  • Retire VMware: Decommissioned cleanly once everything is stable.
  • Handover: Documentation, monitoring and ongoing support.

The conversion technology isn’t the most important part of a VMware to Hyper-V migration. Knowing your environment well enough to move it safely is.

Interactive check

VMware to Hyper-V migration readiness checklist

Tap everything you already have in place. We’ll show how ready you are, and what to sort out next.

Select all that apply

Your migration readiness

Tap the items you have in place.

This is a directional check, not a full migration assessment.

    Decision support

    Which description sounds most like your business?

    Select the one closest to where you are now.

    Your renewal is six months or more away. This is the ideal time. Start with discovery and licensing, so you know what can be reused and whether Hyper-V really makes sense before anything is decided.

    Fast answers

    Quick migration questions

    Tap a question for a short, practical answer.

    Which server should we move first?
    Never your most important one. Start with lower risk VMs to measure real speeds, then move the critical systems.
    Do we have to move everything at once?
    No. Most migrations run VMware and Hyper-V side by side and move workloads in controlled groups.
    Will our printers and applications keep working?
    Usually, with planning. Some software needs reactivating after the move, and printer settings should be documented before any server changes.
    Can we improve our network while we migrate?
    Yes, and it’s often the cheapest time to do it. Separating user systems from backend servers is far easier while workloads are already moving.

    VMware renewal coming up?

    If your renewal is within the next six months, now is the right time to start.

    At Intellect IT, we review your environment, workloads, licensing, hardware and storage to see whether there’s a genuine case for moving.

    If Hyper-V makes sense, we’ll show you what a VMware to Hyper-V migration would realistically involve. If staying on VMware is the better call, we’ll tell you that too.

    QUESTIONS, ANSWERED

    Frequently asked questions

    FAQs – VMware to Hyper-V migration case study

    It depends on the environment, not just the number of VMs. Simple environments with supported operating systems and compatible hardware can move quickly. Projects with new hardware, large data volumes, older systems or tight outage windows take longer. We recommend starting around six months before your VMware renewal.

    For individual workloads, planned outages in our projects have ranged from around one to two hours for smaller systems to four to seven hours for larger systems that need migrating and testing. Workloads are moved in groups, so the whole business is not down at once.

    Often, yes. In one project, an existing SAN was connected to a two-node Windows Server 2025 Hyper-V cluster as Cluster Shared Volume storage. The hardware, storage and licensing need checking first to confirm they suit the new design.

    Not necessarily. Servers and storage with useful life left can often be reused. You do need enough temporary storage to run the migration, which is easy to overlook.

    Common issues include very large VMs that do not fit in the available migration storage, older operating systems, BIOS and partition compatibility, applications that need reactivating, and backups that need moving at the right time. None of these stop a migration if they are found during planning.

    Yes, if it is planned. Keeping VMware and Hyper-V running side by side, and retaining the original VMware VMs until the new ones are tested, gives you a way back.

    Backups need their own plan. Backup services are reconfigured for the Hyper-V workloads and validated, monitoring is updated, and only then is the VMware protection removed.

    Common options are Microsoft’s free Windows Admin Center VM Conversion extension, StarWind V2V Converter for standalone ESXi hosts, Veeam Backup & Replication for larger production workloads, and System Center Virtual Machine Manager for businesses already using System Center. The right choice depends on the size of the environment, the budget and how much downtime each workload can accept.

    Yes. Microsoft’s VM Conversion extension for Windows Admin Center is free and migrates VMs from vCenter to Hyper-V with minimal downtime. It is still in preview, so Microsoft does not formally support it yet, which is worth weighing up for critical systems.

    When the environment genuinely needs what VMware offers, such as a stretched vSAN design across two data centres with automatic failover and complex disaster recovery requirements. The right platform is the one that fits the environment.